Project history

leistungen2.jpg
leistungen.jpg

Here you will find an overview of the projects successfully completed by Ingenieurbüro Sebastian Peschke in the period 2015 to date. If you have any questions about our experience and services, please do not hesitate to contact us.

Project with chargeable costs > 1 mio. € MEP volume: 

Project „Tenant fit-out, LEED legwork”, Frankfurt (2024-2025)

Planning legwork for external LEED consultant (substitute performance)

Trade: ventilation
RIBA stage: 4

Responsibility: MEP design planning and consulting

MEP volume: n.a.
Reference: ISG Germany

Project „Tenant fit-out Opernturm”, Frankfurt (2023-2025)

Planning of tenant fit-out (modern office space) on 6 floors in the Opernturm high-rise

Trade: technical systems for building services
RIBA stage: 3

Responsibility: MEP design planning, construction monitoring

MEP volume: n.a.
Reference: Deerns France: GDM

Project „Frankfurter Office Center, Cooling power control”, Frankfurt (2023-2024)

Replacement of the central control system for the chillers (approx. 4.5 MW) and hybrid coolers during operation.

Trades: cooling, building automation
RIBA stage: 4

Responsibility: project lead, MEP design planning, construction monitoring

MEP volume: n.a.
Reference: Aroundtown

Project „Frankfurter Office Center, Capex measures ”, Frankfurt (2023)

e.g. creating schematics and schematic floor plans of the mechanical systems for the high-rise complex; optimizing the central ventilation systems 5x75,000 m³/h including humidifying and dehumidifying systems and water treatment; eliminating planning deficiencies.

Trades: sanitary, heating, ventilation, cooling, building automation
RIBA stage: 4

Responsibility: Project lead, MEP design planner, coordination

MEP volume: n.a.
Reference: Aroundtown

Project „Shopping Center”, Gießen (2023)

Planning support for technical acceptance of smoke extraction systems in a shopping center, updating of the fire control matrix

Trades: ventilation, building automation
RIBA stage: 4

Responsibility: external consulting
Reference: Ginova Propco

Project „Shopping Center”, Gießen (2022)

MEP design planning for a food court in a shopping center

Trade: sanitary, heating, ventilation, cooling, use-specific systems


RIBA stages: 4

Responsibility: external project lead and MEP design planner

MEP volume: approx. 8 mio. €
Reference: Deerns

Project „Air conditioning for a tea bag production hall”, Hamburg (2022)

Planning of process cooling and ventilation, air conditioning for the hall and compressed air systems

Trades: heating, ventilation, cooling, building automation
RIBA stage: 2 

Responsibility: external project management and MEP design

MEP volume: approx. 4,5 mio. €
Reference: Deerns: Milford

Project „Tenant fit-out office building”, Aachen (2022)

MEP design planning for tenant improvements, office space, production areas, and workshops

Trades: sanitary, heating, ventilation, cooling, building automation
RIBA stage: 2 

Responsibility: MEP design

MEP volume: approx. 2 mio. €
Reference: Deerns Germany

Project „TIER IV Data Center 2x700 kW”, Munich (2019-2022) 

Planning of a high-efficiency data center for a new campus building. Challenge: BIM collision resolution.

Trade: technical systems for building services


RIBA stage: 4 

Responsibility: external project lead and design,  coordination of construction monitoring

MEP volume: approx. 10 mio. €
Reference: Deerns Germany: P7S1 

Project „support Commissioning of a high rise building”, Frankfurt (2021-2022) 

Planning and coordination of capex measures, support for a client during commissioning and snag rectification

Trades: sanitary, heating, ventilation, cooling, building automation
RIBA stages: n.a.
Responsibility: project lead, MEP design planning, MEP construction management 

MEP volume: approx. 1 mio. €
Reference: Aroundtown 

Project „Tenant fit-out Bundesbank“, Frankfurt (2018-2021) 

Planning of tenant fit-out in a 43-storey high-rise. Challenge: Conversion during ongoing building operations, fire protection requirements, coordination with several client representatives, tenants, project managers and specialist planners. 

Trades: sanitary, heating, ventilation, building automation
RIBA stages: 1 - 4
Responsibility: external project lead and MEP design
MEP volume: 7 mio. €
Reference: Deerns Germanys: Aroundtown

Project „Optimization of mechanical engineering for new high-rise construction“, Berlin, (2019-2020) 

Technical advice and support for a general contractor in an open-book procedure. Preparation of trade estimates including cost calculations.

Challenge: incomplete BIM planning, cost optimization
Trade: technical systems for building services

RIBA stages: 1 - 3 

Responsibility: external project lead

MEP volume: approx. 65 mio. €

Reference: Deerns Germany: Eiffage 

Project „Due Diligence Report 70 MW Data Center“, Frankfurt (2018-2019) 

Feasibility study for a large data centre in Hattenheim am Main. Coordination of the necessary preliminary investigations. Participation in and organisation of meetings with architects, authorities and energy supply companies.

Trade: technical systems for building services 

RIBA stages: 0, 1 

Responsibility: externe project lead

MEP volume: approx. 60 mio. €

Reference: Deerns Germany: Data4 

Project „Restructuring plan for 4 MW cooling system“, Frankfurt (2018-2019) 

Planning of a renovation concept for the cooling systems on a 43-storey high-rise building. Planning of a 1 MW interim supply. 

Challenge: Conversion during ongoing building operations, installation of components at a height of 140 m, insufficiently documented inventory. 

Trades: sanitary, cooling, building automation 

RIBA stages: 1 - 3

Responsibility: externe project lead and planning

MEP volume: 2,5 mio. € 

Reference: Deerns Germany: Aroundtown

Project „Canteen construction in a high-rise building“, Frankfurt (2018-2021) 

Planning a canteen for 1300 meals per day in an existing high-rise building.

 

Challenge: Conversion during ongoing building operations, fire protection requirements, problematic delivery of large components, low storey heights, very high air volumes 

Trades: sanitary, heating, ventilation, building automation
RIBA stages: 1 - 4
Responsibility: external project lead and MEP design
MEP volume: 3 mio. €
Reference: Deerns Germany: Aroundtown

Project „Modernization of a boiler house“, Haar (2017) 

Conceptual study for the expansion of a historic boiler house with 9 MW gas-fired boilers.


Trade: heating
RIBA stages: 1, 2 

Responsibility: consulting, planning, project lead

MEP volume: 1,5 mio. €
Reference: kbo 

Projects with chargeable costs > 100.000 € MEP volume: 

Project: “Preparation of a feasibility study for decentralized humidification of office spaces” Frankfurt (2025)

Service phases according to RIBA stages: 1+2

Responsibility: Planning

MEP volume: N.A.

Reference: Project FBC Frankfurt GmbH

Project: “Preparation of a feasibility study for the retrofitting of reheaters in large air handling units” Frankfurt (2025)

Service phases according to RIBA stages: 1+2

Responsibility: Planning

MEP volume: N.A.

Reference: Project FBC Frankfurt GmbH

Project: “Preparation of a feasibility study for emergency cooling of a security control center” Frankfurt (2025)

Service phases according to RIBA stages: 1+2

Responsibility: Planning

MEP volume: N.A.

Reference: Project FBC Frankfurt GmbH

Project: “Preparation of a feasibility study for emergency cooling of a security center” Frankfurt (2025)

Service phases according to RIBA stages: 1-7

Responsibility: Planning

MEP volume: N.A.

Reference: Project FBC Frankfurt GmbH

Project: “Preparation of a renovation concept for the repair of a gray water utilization system in an office high-rise” Frankfurt (2025)

Service phases according to RIBA stages: 1-2

Responsibility: Planning

MEP volume: N.A.

Reference: Project FBC Frankfurt GmbH

Project: “Creation of a renovation concept for the sanitary facilities of a non-residential building” Karlsruhe (2025)

Trades: sanitary

Service phases according to RIBA stages: 0-2

Responsibility: Planning,

MEP volume: approx. €300,000

Reference: xxx GmbH

Project: “Optimization of the heating distribution network of an office building” Frankfurt (2025-2026)

Inventory and creation of documentation, heating load calculation, planning of a water treatment plant, replacement of radiators, valves, installation of fittings for hydraulic balancing

Trades: heating

Service phases according to RIBA stages: 1-8

Responsibility: Project management, planning, construction management

MEP volume: approx. €300k

Reference: Project FBC Frankfurt GmbH

Project: “Optimization of the main heating distribution network of an office high-rise” Frankfurt (2025-2026)

Inventory and creation of documentation, recalculation of hydraulic balancing, renewal of DDC technology, replacement of frequency converters, addition of weak point and constant pressure controls, visualization in central building management system, conversion during ongoing operation

Trades: heating, building automation

Service phases according to RIBA stages: 1-7

Responsibility: Project management, planning

MEP volume: approx. €500,000

Reference: Project FBC Frankfurt GmbH

Project: “Thermal simulation for retrofitting sun protection film on a high-rise facade” Frankfurt (2025)

Service phases according to RIBA stages: 1-2

Responsibility: Planning

MEP volume: N.A.

Reference: Project FBC Frankfurt GmbH

Project: “Renovation of the cooling control system of a high-rise building” Frankfurt (2024-2025)

Switch cabinet conversion during ongoing operation, control of 5 large refrigeration units and 9 hybrid recooling systems

Trades: ventilation, building automation

Service phases according to RIBA STAGES: 1-8

Responsibility: Project management, planning, construction management

MEP volume: N.A.

Reference: Aroundtown

Project „Renovation of building automation Leitz Stuttgart“, Stuttgart (2024-2025) 

Planning of a renovation concept for the building automation of an office building during ongoing operations.

Trade: building automation

RIBA stages: 1 – 4, authorization planning 

Responsibility: consulting, planning, project lead, construction monitoring

MEP volume: 300 k€ 

Reference: Project Mecklenburg Vorpommern GmbH

Project „Prediagnostic vibration measurement retrofit for large ventilation units”, Frankfurt (2024-2025)

Retrofitting of vibration sensors for the early detection of bearing failure due to wear in fans.

Trade: building automation
RIBA stages: 4

Responsibility: planning, consulting, construction monitoring

MEP volume: n.a.
Reference: Aroundtown

Project „Renovation of cooling systems Leitz Stuttgart“, Stuttgart (2023-2025) 

Planning of a refurbishment concept for the cooling systems for an office building during operation.

Trades: cooling, electrical installations, building automation

RIBA stages: 1 - 4 incl. authorization planning

Responsibility: planning, consulting, project lead and construction monitoring

MEP volume: 500 k€ 

Reference: Project Mecklenburg Vorpommern GmbH

Project „FBC Pavillon“, Frankfurt (2023-2024) 

Conversion of an event room, adaptation of the ventilation and cooling system.

Trades: sanitary, ventilation, cooling, building automation

RIBA stages: 2 – 4 incl. authorization planning

Responsibility: planning, consulting, project lead and construction monitoring

MEP volume: 150 k€ 

Reference: Deutsche Bundesbank

Project „Renovation of the canteen's compound cooling system kbo“, Haar (2022-2025) 

Replacement of a compound refrigeration system during operation, conversion to CO2 refrigerant (CO2 booster system with emergency cooling via drinking water and with optional well connection).

Trades: cooling, electrical installations, building automation
RIBA stages: 1 – 4 incl. authorization planning

Responsibility: planning, consulting, project lead and construction monitoring 

MEP volume: 700 k€
Reference: kbo 

Project „High-rise building interim ventilation supply”, Frankfurt (2023)

Design and planning of an interim ventilation unit to replace a 75,000 m3/h ventilation unit for the ventilation of a high-rise building in order to counteract rent payment defaults until the ventilation unit is repaired.

Trade: ventilation
RIBA stages: 1 – 4 incl. authorization planning

Responsibility: planning, consulting, construction monitoring 

MEP volume: n.a.
Reference: Aroundtown

Project „Laboratory air conditioning for prototype production, 3D printing", Munich (2023)

Planning of a technical system for process cooling and air conditioning for a 3D printing area and for adjoining rooms.

Trades: sanitary, ventilation, cooling, building automation
RIBA stages: 3 – 4 incl. authorization planning

MEP volume: approx. 500 k€

Reference: BSH

Project „ New timber-framed building Kita“, Frankfurt (2019-2020) 

MEP design planning of a new timber-framed Kindergarten building (approx. 800m²)

Trades: sanitary, heating, ventilation, building automation
Responsibility: external project lead and planning

Volumen: approx. 250 k€
Reference: Deerns: Aroundtown 

Project „1+2 detached house in the energy network“ (2016-2018) 

Construction of a new single- and two-family house with pellet heating, solar panels, local heating network, electricity network for four buildings with own electricity marketing and eight car charging stations. 

Challenge: complex approval process for the electrical systems, buffer storage tank charging management with weather forecast.

Trades: sanitary, heating, ventilation, electrical installation, outdoor facilities
RIBA stages: 1 – 4 incl. authorization planning
Responsibility: project lead, planning, construction monitoring
Volumen: 300 k€
Reference: IBSP: Rappl 

Project „Residential complex with 25 micro-apartments”, Munich (2017) 

New construction of a residential complex in Munich with 25 luxury apartments.

Trades: sanitary, heating
RIBA stage: 4

Responsibility: Planning and tendering support 

Volumen: n.a. 

Reference: Kamodul 

Project „Bathhouse Föhrenwald“, Wolfratshausen (2015-2017) 

Conversion of a historic building into a museum (900 m²) with a rental area in the basement.

Challenges: non-profit project, unknown inventory.

Trades: sanitary, heating


RIBA stages: 1 – 4 incl. authorization planning

Responsibility: project lead, construction management, planning

Volumen: 130 k€
Reference: IBSP: Badehaus Föhrenwald

Project „Extension of apartment building”, Marquartstein (2016) 

Trade: sanitary, heating, ventilation, electrical installation, outdoor facilities

RIBA stages: n.a. 

Responsibility: Consulting, conceptual design

Volumen: 400 k€ 

Reference: IBSP